Project scope
- piping, pumps, fittings, measurement technology
- complete electrical engineering incl. visualization
Specifications
- Collecting tank
- 28 storage tanks a 100 m³
- 2 matrix distributors for 8 filling lines
- 17 pigging lines
- Erection of the plant during running production